Change of maintainer or acquisition: transferring the ESP file
New service provider or site acquisition: what to recover, and what the 2017 order says about the file, the inspection plan and the requalification.
By cDESP team5 min read
The moment when files get lost
A maintenance contract that ends, a site that is bought, an operator taking over a warehouse with its installations: these are the moments when the history of pressure equipment (ESP, équipements sous pression) most often disappears. Not through ill will, but because the documents were with someone else, in a format nobody can read any more.
Two situations need to be distinguished, because the regulations do not treat them in the same way:
- a change of maintenance contractor (mainteneur): the operator (exploitant) stays the same, only the service provider changes;
- a change of operator: purchase of the site, transfer of the installations, takeover of a lease with the equipment.
The references below are to the arrêté du 20 novembre 2017 relatif au suivi en service des équipements sous pression (French ministerial order of 20 November 2017 on in-service monitoring of pressure equipment).
Case 1: change of maintenance contractor
What the text says
Nothing specific, and that is logical: the operating file (dossier d'exploitation) and the equipment list are obligations of the operator (article 6). The outgoing maintenance contractor has no regulatory obligation of its own to "hand over the file", because that file should have been the operator's from the start. In practice, it is the contract that organises the return of documents. Reread it before the service ends.
What to recover
- the up-to-date equipment list, in a usable format (not just a PDF);
- for each item of equipment, the manufacturing documents: instructions, declaration of conformity, identification and settings of the safety accessories;
- the log of operations, and all certificates: inspection reports, requalification certificates, commissioning inspections, inspections after interventions;
- the inspection plans, with their approval and the history of their modifications;
- the initial verification reports for installations monitored under the CTP (cahier technique professionnel, professional technical code);
- photos of the nameplates, refrigeration diagrams and tags.
What changes with the new service provider
The competent person. The competent person (personne compétente) is designated by the operator (article 2). If they belonged to the outgoing maintenance contractor, a new designation is needed. Note the switchover date.
The inspection plan. It remains the operator's. The new service provider should read it before its first intervention, check that the planned due dates are achievable and report anything that no longer matches the reality of the site. Any modification is made under the conditions of the CTP and must be recorded (article 13).
Due dates. Recalculate the next inspections and requalifications from the latest documents, not from the list handed over. A discrepancy between the two is a warning sign.
Case 2: site acquisition or change of operator
What the text says
Three provisions of the order govern this case:
- The file follows the equipment. Article 6-II provides that the operating file is passed on to the new operator in the event of a change of site or owner.
- So does the inspection plan. Article 13-VII states that, if the equipment changes operator, the inspection plan is transferred with the documentation. The new operator has three options: apply it if the operating conditions are identical, draw up a new plan, or monitor the equipment without an inspection plan, under the default regime.
- Requalification in certain cases. Article 18-II provides that the periodic requalification of fixed equipment is renewed when it undergoes both installation in another establishment and a change of operator. In addition, article 10 requires a commissioning inspection when equipment is put back into service after a new installation outside the establishment where it was used.
When the equipment stays in place and only the operator changes, these two conditions are not met at the same time. If your operation includes dismantling and reinstallation elsewhere, or if the CTP you apply contains specific provisions for a change of operator, have the situation validated by your authorised inspection body (organisme habilité) before putting the equipment back into service.
Due diligence before signing
For a buyer, the state of pressure equipment monitoring is part of the technical audit. Before signing, ask for:
- List 6-III and a sample of equipment files;
- the latest requalification certificates and the latest inspection reports;
- open observations and non-conformities being dealt with;
- the inspection plans and their approval status;
- the commissioning declarations for the equipment concerned.
An overdue date discovered after signing becomes your problem from the transfer onwards.
Steps not to forget
- Commissioning declarations. They are filed by the operator on the LUNE online service (article 9) and contain its contact details. Ask your DREAL (the regional environment authority) about the procedure to follow so that the information reflects the new operator.
- The competent person and the authorised inspection body. New designation, new contracts if needed.
- CTP feedback. If the installations are monitored under the CTP "Systèmes frigorifiques sous pression" (pressurised refrigeration systems), it is now you who send the feedback to La Chaîne Logistique du Froid, as provided by the decision approving the 2026 CTP.
The handover report: one page that saves months of searching
Whatever the case, formalise the handover in a report (procès-verbal de remise) signed by both parties. It fits on one page and serves as the starting point for the new person in charge.
| Section | Content |
|---|---|
| Scope | Sites, installations, number of items of equipment on the list |
| Documents handed over | List, files, inspection plans, certificates, format (paper, files, export) |
| Gaps found | Equipment without a file, illegible nameplates, missing certificates |
| Upcoming due dates | IP (periodic inspection) and RQ (periodic requalification) in the next six months |
| Open observations | Unresolved inspection remarks, actions in progress |
| Roles | Designated competent person, authorised inspection body, contacts |
| Switchover date | From when the new party is responsible |
The gaps found do not disappear because they are written down, but they stop being a surprise. For equipment whose nameplate is lost, see our method for reconstructing the data.
Avoiding the problem next time
The safest way to succeed with a handover is never to let the file leave the operator:
- one digital file per site, which the operator keeps access to whatever the service provider;
- a stable folder structure, identical from one site to the next, that any new technician understands;
- open formats (PDF, spreadsheet) rather than a service provider's proprietary database;
- an annual review of the completeness of the files, not just of the due dates.
With cDESP
In cDESP, each site's file lives in a space that belongs to the client: documents, log, equipment list and due dates. A maintenance contractor can manage several clients and a client can change service provider without losing anything, since access is managed by group. The ZIP export of a site's regulatory file produces all the documents at once, organised in the same folder structure, which is useful for a sale or a due diligence.