Planning
Deadlines and reminders
How cDESP works out the next IP and RQ dates, where to see your deadlines and how the email reminders work.
4 min read
For each system on your sites, cDESP works out the date of the next periodic inspection and of the next periodic requalification. It shows these dates and reminds you of them. This page explains where the dates come from, where to see them and which reminders you get.
Words to know
- ESP: pressure equipment (équipement sous pression).
- System (or set): a group of pressure equipment followed together on a site.
- VI: initial inspection (visite initiale), the first check of the installation.
- MES: commissioning date (mise en service) of the installation.
- IP: periodic inspection (inspection périodique).
- RQ: periodic requalification (requalification périodique), carried out by an authorized inspection body (OH).
How cDESP works out the next dates
Each system has an IP periodicity and an RQ periodicity, entered in its record. cDESP adds this periodicity to a start date. The start date is chosen in this order:
| Next date | Start date, by priority |
|---|---|
| Next IP | 1. the most recent of the last IP and the last RQ · 2. the commissioning (MES) date · 3. the VI date |
| Next RQ | 1. the last RQ · 2. the commissioning (MES) date · 3. the VI date |
Why the last RQ counts for the IP: a requalification includes an inspection. Example: a system had its last IP in March and its last RQ in September of the same year. The next IP starts from September, the most recent date.
If the periodicity or every start date is missing, cDESP computes nothing. A date already entered by hand is kept.
Where to see your deadlines
The intervention calendar
- In the left menu, click Planning.
- Scroll down below the appointments: the list of your sites appears.
- Click a site to show the table of its systems.
For each system, the table shows: State, Model, VI Date, Last IP, Last RQ, Next IP and Next RQ.
An icon in front of each site sums up its situation. The filter buttons above the list keep only the sites you want:
- Pending: the site is not complete yet.
- Compliant: every system has a VI date and no deadline has passed.
- Overdue: a VI date is missing, or an IP or RQ is past due.
A system marked with a moon is dormant (shut down). It is not counted.
To record an inspection that was done:
- In the system row, click the Last IP or Last RQ box.
- Pick the date in the calendar.
The next date updates at once. A new RQ also updates the next IP.
The notification bell
The bell sits at the top of the left menu (on a phone, at the top of the screen). A dot means something new. Click it to open the Regulatory deadlines list. It groups, site by site:
- overdue IPs and RQs, in red;
- IPs due within the next two months;
- RQs due within the next six months;
- systems with an incomplete regulatory record.
Click a site to open it.
The system record
The Next IP and Next RQ fields of the system record show the same dates. See Equipment and nameplates.
Email reminders
Accounts with a subscription get a summary email for the sites of their groups. It lists, site by site, the systems whose IP or RQ is coming up or past due, and those with an incomplete record. It may also offer to request a quote from DCRR for these interventions.
- The email is sent only when there is something to report.
- It arrives every week or every month, depending on your subscription.
- It is written in French.
- If you use the mobile app, a notification may also reach your phone.
Stopping or restarting the reminders
The Receive regulatory reminders by email option is on by default for every account. The DCRR team sets it. To stop or restart these emails, write to the team through the messaging: see Contact DCRR.
Missing dates
cDESP flags an incomplete regulatory record when a system has no VI date, no next IP or no next RQ. Dormant systems are ignored.
To fix it, complete the system record: VI date, commissioning (MES) date, last IP, last RQ and periodicities. The next dates are then worked out automatically.
To set the date with the inspection body, see Appointments with inspection bodies.